SRT backs 122.7-billion-baht southern double-track plan
Compiled by KHAO Editorial — aggregated from 1 outlet. See llms.txt for citation guidance.
◌ Single Source
The State Railway of Thailand (SRT) board has endorsed a revised investment framework of 122.72 billion baht for three Phase 2 double-track railway projects in southern Thailand.
Key facts
- The new budget is 18.2548 billion baht higher than the previous combined framework of about 100 billion baht, SRT Governor Anan Phonimdang said following the board meeting on Tuesday (August 11).
- SRT aims to begin construction around July 2027.
- The Chumphon–Surat Thani section is expected to take 60 months and be completed in 2032
- The Surat Thani–Hat Yai section is scheduled to take 72 months, with completion targeted for 2033.
- The Hat Yai–Padang Besar section is expected to take 48 months and be completed in 2031.
Summary
The new budget is 18.2548 billion baht higher than the previous combined framework of about 100 billion baht, SRT Governor Anan Phonimdang said following the board meeting on Tuesday (August 11).
The package covers the Chumphon–Surat Thani, Surat Thani–Hat Yai Junction–Songkhla and Hat Yai Junction–Padang Besar routes. However, the Hat Yai Junction–Songkhla section will be deferred while the railway authority prioritises the main corridors.